Thank you, Richard, and hello to everybody. So turning to Slide 5. During my first 3 months with i-80, I've had the chance to evaluate our operations and development projects. We determine their technical status, additional work required and to identify opportunities to optimize execution, ramp up of personnel and potentially accelerate timelines. Some initial observations stand out. We have a solid geological understanding of our assets, underpinned by high-grade resources with meaningful growth upside. The supporting technical work required is relatively low risk positioning us well to advance our projects with confidence. We have a significant resource base with 6.5 million ounces of measured and indicated gold resources and 7.5 million ounces of inferred resources following prior years of extensive drilling and as well, approximately 100 million ounces of silver in each of the 2 categories. The 2025 drill program is progressing well, with a focus on infill drilling to advance technical studies. Next, we have access to a deep bench of experienced operating and technical mining talent. Our team brings decades of technical and operating experience from other major mining operations in Nevada. Recently, we have hired additional personnel in Reno and at the operations to execute on our growth plan. Next, we have industry-leading environmental, health and safety systems and controls. And lastly, i-80 has an established presence in the local community and trusting relationships with regulatory agencies, creating pride and commitment within our workforce. Moving to Slide 6 for a look at Granite Creek underground. Mining volumes during the second quarter were ahead of the prior year period. We mined approximately 24,000 tons of oxide mineralized material at a gold grade of 11.4 grams per tonne and approximately 11,200 tons of sulfide material at a gold grade of 7.4 grams per ton, plus an additional 16,000 tons of incremental low-grade oxide material at a gold grade of 3 grams per ton. For the quarter, just under 6,000 ounces of gold were sold, of which approximately 1/4 of the ounces were leached and sold from the Lone Tree heap leach facility. Approximately 28,000 tons or 7,000 ounces of sulfide mineralized material were stockpiled for processing at a third-party facility. We are encountering higher-than-expected levels of oxide mineralized material at Granite Creek underground compared to our March 2025 PEA. On the dewatering program, the team has shifted to a more proactive long-term approach and continues to upgrade the infrastructure. These upgrades include the planned installation of 2 additional surface dewatering wells, which is one more than initially planned at the beginning of the year based on the new predictive groundwater model. It includes expansion of the water treatment facility and upgrades to the existing underground water management infrastructure. We expect groundwater inflows to remain at or near the current ingress rates for the foreseeable future. However, by installing these mitigation measures, water inflows are not expected to impede our development planning for the long term. With the proper dewatering infrastructure in place, continued drilling, further technical work over the next 6 to 12 months, Granite Creek has the potential to be an excellent asset for us. At Lone Tree and Ruby Hill, we continue recovering gold from the existing leach pads with approximately 2,400 gold ounces recovered and sold in the second quarter. Company-wide, we expect to extract between 30,000 to 40,000 ounces of gold in 2025, in line with guidance. This includes 20,000 to 30,000 ounces of gold from Granite Creek and approximately 10,000 ounces from the heap leach pads. At Granite Creek underground, we completed the underground exploration drift, providing access for infill drilling in the prospective South Pacific zone. We currently have a total of 2 rigs underground and 3 at surface with more than 40 holes planned for a total of approximately 46,000 feet. The program is designed to upgrade the mineral resource and form the basis for the upcoming feasibility study planned to be completed for the first quarter of 2026. Next, let's turn to Slide 7 for an update on our second planned underground mine. At Archimedes, the upper level permitting is nearly complete, which covers mining activities above the 5,100 foot level, while we focus on geochemistry and technical studies to support permitting needed for the lower levels. With surface infrastructure to support the portal now complete, development of the underground exploration drift is scheduled to commence in the next several weeks. Infill drilling of the Upper