Slide 5. Thank you, Richard. The new development plan is focused on near-term cash flow generation, advancing a pipeline of growth. We are now focused on the ramp up permitting and development of five gold deposits through the balance of the decade, including three underground mines, and accelerating the permitting and development of two large oxide open pit deposits, Granite Creek and Mineral Point. The Lone Tree Autoclave remains the centralized refractory ore processing facility in the new development plan and management intends to continue its work towards completion of the refurbishment feasibility study next year. Following the completion of the study, a series of trade-off scenarios will be considered comparing full autoclave refurbishment to alternate toll milling and ore purchase agreement options that could potentially be available. Slide 6, Granite Creek is comprised of an underground mine, which is currently ramping up and expected to be in commercial production in 2026, an open pit project that is in the permitting process. Slide 7, as mentioned, Granite Creek Underground is currently ramping up to commercial production. Mining rates and gold production for the quarter and nine months of 2024 were lower than planned due to an increase in ground water ingress into the underground working areas, which negatively impacted productivity and development advancement rates. To address the higher water rates, the mine is adding additional pumping capacity, deepening an existing de-watering well and reworking the de-watering system to allow for additional flow capacity in the water treatment facility on site. We expect that production and costs will continue to be negatively impacted until these measures are completed and groundwater flows return to easily manageable levels, which is expected to occur by the end of the third quarter 2025. On a positive note, the ore control reconciliation on the bench level in the two zones mine to-date has been positive. In the Ogee zone where most mining has occurred we have seen more tons plus 40% better grade plus 37% or more ounces plus 90%. On the first level of the South Pacific zone we saw nearly a three-fold increase in tons at expected rate for nearly 3x more ounces. As a result, we feel confident that once we address the water issues, costs will decline and production will increase. This is also the asset that we believe has the most exploration upside given its location of less than 10 km from a world class mine with over 25 million ounces discovered to-date. Slide 8, the Granite Creek open pit is a relatively low capital intensity project given that it is a previously producing mine using heap leach processing. The mineral resource sits at over 1 million ounces at an average grade of approximately 1.4 grams per ton, making it one of the highest grade oxide deposits in Nevada. The 2021 Pre-Feasibility Study envisioned the heap leach and mill standard. We are updating the prior technical report and we will perform trade-off studies of heap leaching the entire deposit, building an oxide processing facility on-site or utilizing process infrastructure already in place at other properties to process the higher grade material through a mill while continuing to heap leach the lower grade material. This study is expected to be released near the end of 2025. We have begun the permitting process. We expect the process will take approximately three years followed by 18 months of construction. Slide 9, Ruby Hill Complex is comprised of the Archimedes Underground formerly known as the Ruby Deeps. The Mineral Point oxide open pit project as well as the Gold Hill oxide deposit. Additionally, the Ruby Hill Complex hosts significant base metal potential at the FAD project, Blackjack, and Hilltop. For the time being, base metal projects and the Gold Hill project have been deferred to focus on the more advanced gold projects that have a clear and shorter pathway to generating free cash flow. Ryan will expand on the base metal JV later on the call. Slide 10, we expect permits for underground mining at Archimedes in Q1 of 2025, allowing us to begin development and achieving production in late 2026. Archimedes Underground is on track to be our second producing asset. While it has the lowest grade of our three underground mines, it has the most favorable mining conditions, which will allow us to mine the deposit utilizing more efficient mining methods. As we develop the lower portion of the ore body, we will complete the required drilling to permit the lower portion of the ore body over the next few years. We will have a PEA for Archimedes Underground by the end of Q1 2025. However, we anticipate that we will not issue a feasibility study on the Archimedes Underground until we complete the drilling program, which is currently targeted for 2027, once construction of the underground drill platforms are completed. Therefore, we envision the Archimedes feasibility study to be published in late 2027 or early 2028. Slide 11, Mineral Point has the potential to be our flagship mine. It hosts our largest gold and silver resource in the portfolio. Based on the internal scoping study, it has the potential to be a multi-hundred thousand ounce mine at solid cost. It will be our most expensive mine to build, but the expectation is that by the time we begin construction targeted for 2030, we anticipate to have four producing gold mines generating significant cash flows to fund the development of Mineral Point in combination with the project finance or corporate facility, we expect to release a PEA in Q1 2025. Slide 12, Cove is our third underground mine. Like Granite Creek, grades are over 10 grams per ton, making it one of the highest grade underground mines in North America. The mining conditions at Cove were better than Granite Creek, but perhaps not as favorable as Archimedes. The baseline work to advance our final permit application is proceeding on schedule. We expect to submit the final permits in mid-2025 and expect final approvals by the end of 2027. Construction is scheduled to take 18 months. Construction scope of work consists of de-watering and portal development with associated infrastructure. There is no planned processing facilities at Cove. An infill drill program is underway. It is expected to be completed in Q1 of 2025, which will allow us to finalize the feasibility study for the mine in 2025. Slide 13, I've already spoken to the pending feasibility study, which will allow us to optimize the value of the permitted autoclave at Lone Tree. We continue to realize value for the oxide material mined at Granite Creek through the existing ore purchase agreement while we pursue alternatives for the processing of our refractory material either through an extension of our toll milling agreement or alternate processing solution. The Lone Tree open pit project, however, continues to have a variety of financial, technical, environmental and social issues to be worked through. It is expected the project will likely remain deferred for another decade. We believe new technologies and other solutions may become available in the future to allow us to unlock the value of this large open pit project. Slide 14, we mined over 53,000 tons of Granite Creek underground nearly 50% more than Q3 of last year. Mining of processing grade material, which is grade equal or above 5 grams per ton is largely in line with last year's production. An overall increase in the number of mining headings available has allowed for comparable production in spite of the de-watering issues discussed earlier. The significant increase in oxide mineralized material mined when compared to 2023 is due to the inclusion of oxide material grading between 2 and 5 grams per ton. When oxide mineralized material grading in this range is encountered, this material is classified as incremental material and transported to the Lone Tree facility for leaching on the heap leach pads at that site. For clarity, no stopes are planned at less than 5 grams per ton. The incremental material is encountered when developing the decline or while accessing to or between stope blocks. Development rates continue to ramp up when compared to the same period in 2023 but still are not meeting our plan again due to water. Sharp reduction in exploration drilling footage is a function of both a large exploration drilling program in 2023, as well as shifting our strategy for exploration drilling from surface to underground in 2024. This shift has delayed our timing of drilling as we complete the excavation of the underground drilling platform. I will now hand the call over to Ryan Snow to walk us through our financials.