Thank you, Alex. Thank you everyone for joining us today. Slide one. As many of you know, I joined Ur-Energy Inc. midway through 2025. From my perspective, it was a year of strong execution and meaningful progress. Across our operations, development pipeline, and financial position, we delivered tangible improvements that position the company for production growth in 2026. Slide two disclaimer. As Alex mentioned, we will likely make forward-looking statements today. Please read the disclaimer at your leisure. On to Lost Creek, Slide three. At Lost Creek, our focus on operational execution translated into significant year-over-year gains. We ended the year with 406,000 pounds of product in inventory, an increase of 21% over 2024. We increased pounds drummed in 2025 by 65% over 2024. We also improved wellfield flow rates, increased pounds captured by 40%, and increased our profit per pound sold by more than $12. Our average cash cost per pound sold, including severance and ad valorem taxes, was $42.89. These results reflect stronger wellfield performance, improved plant throughput, and disciplined operating focus. Slide four. Ongoing drilling at Lost Creek continues to create value. As detailed in our updated S-K 1300 technical report, the measured and indicated resource is now estimated at 11,900,000 pounds and the inferred resource is at 10,400,000 pounds. The estimated mine life at Lost Creek was extended by nearly three years, and the post-tax net cash flow increased to $442,000,000, roughly 45% more than the previous estimate. The NPV with an 8% discount rate is now estimated at $244,000,000, with an internal rate of return of almost 66%. Slide five. We still only drilled a portion of the more than 35,000 contiguous acres at the Lost Creek property. As our Chief Operating Officer, Mr. Steve Hatten, said in yesterday's press release, every time we drill Lost Creek, we have been fortunate to increase the resource base. This underscores Lost Creek's scale, longevity, and long-term growth potential. On Slide six in Shirley Basin, at our Shirley Basin project, we made substantial progress towards bringing our second ISR production facility online. The initial processing plant construction is nearing completion, with all ion exchange columns installed and heat tanks in place. To support start of operation, we have drilled 469 injection and production wells. In Mine Unit 1, Header House 1 is ready to begin initial injection and recovery from the well pending approval from the state environmental department. They began their pre-operational inspections in late February and are looking at our wellfield data package, so that process is underway. The March 2024 technical report for Shirley Basin estimated a nine-year mine life and 8,800,000 pounds of resource in the measured and indicated categories. The estimated post-tax net cash flow is $119,000,000. The NPV with an 8% discount rate is $82,000,000, and an internal rate of return of 69%. The estimated all-in cost is $50 per pound. During 2025, we grew our Ur-Energy Inc. workforce by 55% and welcomed 56 new team members. The majority of those were added to support Shirley Basin, but we also strengthened our operational, technical, and corporate teams across the company. We are proud of the team we have built. Slide seven. From a financial perspective, we ended the year with $123,900,000 in cash, driven largely by the successful closing of our 4.75% convertible senior notes. Our cash position as of 03/04/2026 is $115,300,000. That does not include $18,500,000 that we will receive this month for $24.724700000.0 warrants that were exercised last month for about 12,300,000 of our common shares. All of our outstanding warrants were exercised over the last few months except for an insignificant number that expired. The strength of our balance sheet gives us the flexibility to fund Shirley Basin commissioning, continue ramp up at Lost Creek, and disciplined resource growth. And while we are not taking any victory laps just yet, it is worth pointing out that we finished the year with a positive gross profit of $74,000. A milestone, but an encouraging milestone, as operations and production continue to improve. On Slide eight, at our Lost Soldier project, we installed 18 aquifer test wells in late 2025 to support the evaluation of the potential for ISR development. Aquifer testing will begin this month, followed by baseline environmental studies for permitting and for additional permit—pardon me. Lost Soldier is just 17 miles from the Lost Creek process plant, which could mean an opportunity to develop it as a satellite operation using our existing infrastructure. We have also started work on a technical report for the project that we expect to complete by the end of this year. At our North Hassel project in the Great Divide Basin, drilling continues to deliver very encouraging early results. Through February, we drilled 32 wide-spaced holes totaling 33,000 feet. Seven of those intersected significant uranium mineralization, including 13 intercepts exceeding our Lost Creek cut-off grade. These results suggest multiple stacked roll front horizons, with grade and thicknesses comparable to Lost Creek, supporting the potential for future ISR development. The results include two standout holes, about 1.5 miles apart, that intersected significant stacked mineralization at similar depths, giving us some early confidence in the potential scale of the system. And North Hassel is only 18 miles from Lost Creek. Once we wrap up the 50-hole program at North Hassel, we will move the rigs over to our Lost Creek South project this summer. Lost Creek South is located adjacent to Lost Creek, and we are planning a 120-hole drill program there this year. These exploration programs are critical to expanding our development pipeline, growing our resource base, and diversifying potential future production across multiple projects. Slide nine, wrapping up. As we entered 2026, we continue to optimize our operations at Lost Creek while our second ISR facility, Shirley Basin, is making significant progress towards startup. Our combined estimated mineral resource totals 21,000,000 pounds in the measured and indicated categories, and 10,400,000 pounds in the inferred category, as of 12/31/2025, providing a strong resource base for our production. We have contracted for sales of 1,300,000 pounds in 2026. We plan to cover those sales with pounds in inventory and new pounds that we produce at Lost Creek and Shirley Basin. And on March 4, we had 379,000 pounds in conversion facility inventory. With our growing resource base and strong balance sheet, we believe Ur-Energy Inc. is well positioned to benefit from positive uranium market fundamentals and increased demand for secure U.S. uranium supply. And with that, I will turn it back to the operator to open it up for questions and answers. Thank you.