image
Utilities - Regulated Electric - NYSE - US
$ 57.63
2.56 %
$ 48.4 B
Market Cap
21.27
P/E
EARNINGS CALL TRANSCRIPT
EARNINGS CALL TRANSCRIPT 2018 - Q4
image
Operator

Ladies and gentlemen, good morning, and welcome to the Dominion Energy Fourth Quarter Earnings Conference Call. At this time, each of your lines is in a listen-only mode. At the conclusion of today’s presentation, we will open the floor for questions. [Operator Instructions] I would now like to turn the call over to Mr.

Stephen Ridge, the Director of Investor Relations for the Safe Harbor Statements..

Stephen Ridge

Good morning, and welcome to the fourth quarter 2018 earnings conference call for Dominion Energy. I encourage you to visit the Investor Relations page on our website to view the earnings press releases and accompanying materials as well as the slide presentation that will follow this morning's prepared remarks.

Schedules in the earnings release kit are intended to answer detailed questions pertaining to operating statistics and accounting, and the Investor Relations team will be available immediately after the call to answer additional questions.

The earnings releases and other matters that will be discussed on the call today may contain forward-looking statements and estimates that are subject to various risks and uncertainties.

Please refer to our SEC filings including our most recent Annual Report on Form 10-K and our quarterly reports on Form 10-Q for a discussion of factors that may cause results to differ from management's projections, forecasts, estimates and expectations.

Also on this call, we will discuss some measures of our Company's performance that differ from those recognized by GAAP. Reconciliation of our non-GAAP measures to the most directly comparable GAAP financial measures which are – we are able to calculate and report are contained in the earnings release kit.

Joining today’s call are, Tom Farrell, Chairman, President and Chief Executive Officer; Jim Chapman, Executive Vice President, Chief Financial Officer and Treasurer and other members of the executive management team. I will now turn the call over to Jim..

James Chapman

Good morning. Dominion Energy reported operating earnings of $0.89 per share for the fourth quarter of 2018, which is above the midpoint of our guidance range of $0.80 to $0.95 per share. GAAP earnings for the quarter were $0.97 per share which includes gains on the sales of non-core assets.

For the full year, we reported operating earnings of $4.05 per share which is also above the midpoint of our guidance range of $3.95 to $4.10 per share.

Drivers relative to our guidance include lower O&M, income tax, depreciation expense, as well as favorable weather, partially offset by a longer commissioning process for the Cove Point liquefaction project during the first quarter and higher storm restoration expense in the third and fourth quarters.

We are pleased that despite a challenging year, we achieved annual operating earnings per share growth of 12.5%. Operating segment performance for the fourth quarter and the full year are shown on Slide 4. GAAP earnings for the year were $3.74 per share.

Differences between operating and reported earnings included gain on sale of non-core assets, unrealized losses on nuclear decommissioning trust bonds, and one-time rate credits issued to customers under Virginia legislation passed in March.

A reconciliation of operating earnings to reported earnings can be found on Schedule 2 of the earnings release kit. Before we turn the page completely on 2018, we want to briefly highlight some of the important initiatives that we successfully executed during the year and that we believe will position us for success in 2019.

As we mentioned, we achieved annual operating earnings per share growth of more than 10% despite a number of headwinds including a dramatically altered financing plan.

We grew the dividend per share by 10% year-over-year consistent with the commitment we had previously made to shareholders and slightly lower than annual operating earnings per share growth.

We sold non-core merchant assets at attractive valuation, improving our business risk profile and generating over $2.5 billion of sale proceeds which we used to retire parent-level debt.

We placed both the Cove Point liquefaction projects and Greenville power station into commercial service collectively representing over $5 billion of invested capital.

I am pleased to report that Cove Point continues to operate at or above design capacity and successfully completed the same day loading of an export cargo and unloading of an import cargo during the fourth quarter, which we believe maybe a first for the domestic LNG industry. Greensville is also operating as designed.

We took meaningful steps to improve our credit profile including reducing parent level debt by about $8 billion through proceeds from equity issuance, non-core asset sales and a Cove Point asset level financing. As a result of these efforts, we achieved our parent level leverage targets two years ahead of schedule.

We also materially improved our cash flow coverage metric as measured by Moody’s. These achievements in combination with the improved business risk profile due to asset sale and the addition of SCANA’s high-quality regulated businesses resulted in the affirmation of our existing credit ratings and the lowering of our credit metric thresholds.

In Virginia, we work with legislators, the Governor, customer groups and other important stakeholders to support the grid transformation and security act, a bipartisan law that provides a path to a sustainable and reliable energy future in the commonwealth.

And finally, we obtained all required regulatory approval and subsequently closed our merger with SCANA, which we expect to provide near-term earnings of approximately $0.10 per share per year.

Tom will speak more about this a little later but we are pleased that we were able to offer significant value to SCANA customers, protection of the SCANA employees, and preserve the transaction economics that our shareholders and credit providers expected. Moving on to 2019 earnings guidance.

Operating earnings per share for 2019 are expected to be between $4.05 and $4.40 per share. This guidance range of $0.35 is narrower than in recent years reflecting the increasingly regulated nature of our operation. The midpoint of this range represents 5.6% growth relative to 2018’s weather-normalized results.

As usual, our guidance assumes normal weather, variations from which could cause results to swing toward or the bottom of this narrower guidance range.

Positive factors as compared to last year included an additional quarter of commercial operations of the Cove Point liquefaction project, the addition of the Southeast Energy Group operating segment which includes all former SCANA operations and growth from regulated investment.

Negative factors as compared to last year include the loss of earnings from 2018 asset sales, a higher share count, higher pension expense and a return to normal weather. The midpoint of our 2019 guidance range assumes that ACP Constructions recommences during the third quarter of this year which Tom will address momentarily.

It excludes any contribution associated with the Blue Racer earn out which could be zero, as well as any contribution associated with the resolution of the outstanding zero carbon energy procurement process in Connecticut, which Tom will also address.

Our operating earnings guidance for the first quarter of this year is $1.05 to $1.25 per share, compared to $1.14 per share in this first quarter of 2018. Positive factors relative to Q1 2018 included the contribution from the Cove Point liquefaction project and the addition of the Southeast Energy Group.

Negative factors include timing of contributions are formed, the loss of earnings from asset sale, and a higher share count.

While we are not providing formal 2020 operating earnings guidance on today’s call, we do expect approximately 5% growth from 2019 to 2020 which aligns with achieving our most recent guidance regarding our 2017 to 2020, 6% to 8% compounded annual growth rate.

This 2020 expectation also excludes the impact of any Blue Racer earn out and the contribution from a resolution in Connecticut. Finally, we expect dividend per share growth in 2019 of 10%. Please note that all dividend declarations are subject to Board approval.

Major elements of our 2019 financial plan are included on Slide 8 in addition to a fairly standard debt financing program, we intend to replace and possibly increase the size of the mandatory convertible security that’s issued three years ago and which converts in the third quarter.

Despite a firm ratings and lower credit metric downgrade thresholds, we will continue to take steps to support our credit profile. Turning to Dominion Energy Midstream Partners. The merger of DM into Dominion Energy was completed earlier this week.

We issued approximately 22 million shares in exchange for all outstanding Dominion Midstream common and preferred units. The merged asset now resides the subsidiary of our parent company, but we intend for certain assets to migrate to Dominion Energy Gas Holdings during the year.

Finally, we plan to make two distinct presentations for investors on March 25th.

The first presentation targeting the general investor community will include a number of informational updates such as asset profiles, asset profile updates including for the newly added Southeast Energy Group, capital investment programs, opportunities under the Grid Transformation and Security Act in Virginia, O&M initiatives and long-term dividend growth and capital structure objectives.

We believe that this brief presentation will provide reference information and insights that will help investors to better understand Dominion Energy’s expanded operational footprint, as well as drivers behind our expectation for 5% plus growth in operating earnings per share beyond 2020.

We are pleased to announce that in a second a super presentation on that day, we will provide an update that will focus exclusively on our accomplishments and efforts about environmental, social and governance matters and how those efforts underpin our long-term strategy and position us to become an industry leader in sustainability.

To our knowledge, this is the first instance of a major company from the energy infrastructure industry or otherwise to host an investor session dedicated exclusively to these matters. The target audience for the second presentation is members of the financial community with special focus on ESG topics.

Both of these presentations will be webcast live on our investor relations website with an opportunity to submit questions electronically, so that in the event of capacity constraints at our New York City venue, all investors will be able to participate. We will be providing additional information regarding these investor updates in the near future.

I’ll now turn the call over to Tom. .

Thomas Farrell

Thank you, Jim and good morning. For the second straight year, we have a set a company record for the lowest OSHA recordable incident rate in our history, 0.55, which is an 8% improvement over what was a record-setting performance in 2017. This achievement is equally impressive when compared to a peer average that is nearly twice as high.

Safety does not just happen. These results represent years of focus on making sure that every employee returns home in the same condition in which they arrived at work that day. We are going to continue to improve until we achieve the only acceptable safety statistic zero injuries. Now to our business updates.

I will begin by addressing our merger with SCANA which closed at the beginning of this year. Our new operating segment, the Southeast Energy Group comprises all of the former SCANA operations. Rodney Blevins, one of our most experienced utility operators now lead the segment.

He is working among the over 5000 able and dedicated colleagues that now comprise the Southeast Energy Group. The Group’s high-quality businesses and our colleagues who operate them enhance Dominion’s best-in-class portfolio of state regulated utility operations.

For example, customer growth at SEG’s electric and gas utilities were 1.7% and 2.8% respectively during 2018. North and South Carolina despite the challenges related to new nuclear development in the latter are considered to be among the most constructive regulatory jurisdictions in the country.

In 2020, we will file a rate case in South Carolina that’s subject to commission approval will reflect recovery of traditional electric utility capital investment that is not currently being recovered in rates. Those new rates subject to approval will become effective on January 1, 2021.

Over the coming months, we will continue to build trust with customers, employees, regulators and policy makers by keeping our commitments and being a transparent and responsible corporate citizen. We look forward to discuss in the Southeast Energy Group in greater detail in our Investor Meeting in March.

Next I’ll turn to updates related to the Grid Transformation and Security Act adopted last year in Virginia. In less than a year, we have filed for and received Virginia State Corporation Commission approval for projects representing over $1 billion of capital investment.

We expect that number to grow significantly over the next several years as we continue to invest to make our system increasingly sustainable and reliable for our customers. First, we received approval from the SEC for our approximately $300 million offshore wind projects which will be completed under a fixed cost construction agreement.

This pilot has to support Governor Northam in Virginia’s General Assembly and will provide important early learnings that we believe will lay the foundation for commercial scale offshore wind for Virginia’s clean energy future. Construction of the project is expected to begin this second quarter with a commercial in-service date in late 2020.

Second, we received approval from the SEC for phases 2 and 3 of our strategic undergrounding program representing a capital investment of about $240 million. This effort improves the reliability of our systems and substantially reduces the duration of restoration times following severe weather events.

Third, we received an order granting our certificate of public necessity and convenience for our U.S. 3 Utility-Scale solar farms representing 240 megawatts at a capital cost of around $410 million.

We remain committed to advancing our goal of having 3000 megawatts of additional renewable generating capacity in service or under development by 2022 and we expect to make regular filings under the GTSA with the commission for additional projects in the future.

Next, we received partial approval from the SEC for our initial grid transformation application. The commission approved nearly $100 million of capital over three years associated with important physical and cyber security investments.

The commission asked for more information to support capital investment associated with other aspects of our Grid Mod strategy including smart meters, intelligence grid devices and an enhanced customer information platform that allows more sophisticated and convenient customer experience.

We will provide that data when we refile our application later this summer. A decision on the refiled application would be expected six months after. I want to offer a few remarks related to recently proposed legislation supported by Governor Northam and bipartisan legislative leadership that establishes a path for addressing our coal ash ponds.

We support the policy makers’ desire to resolve this issue permanently through annual rider recovery. The legislation will provide for full cost recovery of operating expense and capital investment associated with the recycling of coal ash for beneficial use and the construction of on-site lined landfills for disposal of the residual coal ash.

We believe the BET legislation provides a fair balance between Dominion Energy’s customers and its shareholders and allocates the cost of this program equitably among large and small users of electricity. I’ll now address the Millstone and the Atlantic Coast Pipeline.

With regard to Millstone, it is important to recognize the extent of the progress that has been made today on ensuring the long-term viability of this critically important resource to Connecticut. We began engaging in the legislative process for years ago.

We have diligently followed the law and requirements established by both DEEP and PURA and each agency has determined Millstone is an at-risk resource. Former Governor Malloy made an announcement in late December awarding Millstone a ten year agreement for 9 million megawatt hours per year.

The awarded price for the first three years of the contract is approximately equal to the New England wholesale power price. That is not an acceptable result for the company and our 1500 Millstone colleagues who work safely every day to provide half of the power and 90% of zero carbon power to the State of Connecticut.

In order to ensure the plant’s viability, we must have pricing that recognizes energy security, environmental and economic benefits. We have and we will continue to engage constructively with Governor Lamont’s team seeking the solution that works for the state, the region, our company and our employees.

We are confident that these issues will be resolved in a manner that provides long-term financial assurance required for Millstone’s continued operation.

As for the Atlantic Coast Pipeline and supply header projects we remain highly confident in the successful and timely resolution of all outstanding permit issues, as well as the ultimate completion of the entire project for the following reasons.

First, our customers critically need this project to heat and electrify homes, businesses and industries, assist in the transition away from coal-fired power generation, support economic and renewable energy development and reduce reliance on a single source of gas to liquid.

Our customers, state regulatory commissions and FERC have all attested independently to the need for this project. Second, we have followed the established rules with regard to permitting environmental protection, years of painstaking surveying, data collection and scientific analysis needed by all of our permit applications.

In fact, most of our permits are setting new national standards in minimizing environmental impacts. Without speaking for the permitting agencies, these professionals have followed the letter and the spirit of the rules, regulations and established precedence that guided their action on our permit applications.

Third, we are actively pursuing multiple paths to resolve all outstanding permit issues including judicial, legislative and administrative advocates. We are not alone in these positions. We have the support of the agencies, our customers, and varied industry interests. Our current expectation is that full construction to restart in the third quarter.

This reflects our belief that the biological opinion issue in any impediments with the cross in the Appalachian Trail should be resolved no later than this fall.

Based on the scheduled key segments of the project including from Buckingham County located in Central Virginia to the presently planned terminus in Hampton Roads in Eastern Virginia and in Lumberton in Southeastern North Carolina would enter commercial service by the end of 2020 with the balance of the project being delivered in early 2021.

The cost of the project based on this schedule is expected to be $7 billion to $7.5 billion excluding financing cost, an increase of approximately $500 million since the update we provided in November. Similarly, we expect that this supply header project would enter commercial service in late 2020 with a project cost of $650 million to $700 million.

While we believe that the Appalachian Trail crossing issue should be resolved in time to recommence construction along the entire route during the third quarter, we intend to continue to build key segments that will deliver partial service to our customers by the end of 2020.

The completion of the remaining section which could involve an appeal in spring quarter would complement the first phase of service by the end of 2021. Under this alternative, total project cost would increase an additional $250 million resulting in total project cost of $7.25 billion to $7.75 billion excluding financing costs.

In either case, we are currently working with customers to set rates that balance customer needs with preserving a fair project return.

It’s important to understand that the average base is differential, over the last five years has been $1.79 per decatherm which significantly exceeds the rates of this project and of course cost is not the only factor driving our customers’ demand.

Additional and diversified supply is critical, given that they are forced to turn away new customers due to the lack of infrastructure.

When extreme weather occurs, such as the existing polar vortex in the Midwest, or the bitter colds that affected the Mid-Atlantic in both 2016 and 2018, the concept of reliable and redundant energy supply assumes a new and much more serious meaning. Policymakers understand the gravity of the situation.

Disruptions for the region’s limited supply of existing gas delivery infrastructure and weather-driven demand spikes have and will continue to resolve in higher prices, forced curtailments and lower reliability for customers until the project is complete.

To be clear, we believe that there are multiple paths that will allow us to complete the entire 600 mile project. As was the case regarding the challenges we faced in the developments of the Cove Point liquefaction project, and the closing of our merger with SCANA, large projects require transparency and determination. We have in abundance of both.

We will continue to accrue AFUDC equity earnings and expect ACP to contribute to our operating earnings in 2019, 2020 and for decades to come. In summary, during 2018, we set a new company record for safety performance for the second consecutive year.

We delivered 2018 operating earnings per share that exceeded the midpoint of our guidance range and initiated 2019 guidance that implies over 5% annual growth to 2018 weather-normalized results. Our 2019 dividends per share are expected to grow 10% subject to Board approval.

We successfully executed several major initiatives including merchant asset sales, $8 billion of parent level debt reduction, the buy-in of Dominion Energy Midstream Partners and the commercial in-service of the Cove Point liquefaction project and Greensville Power Station that support our earnings and credit objectives and position the business to continue to deliver visible, diversified and regulated growth in the future.

We completed the SCANA merger adding exciting new businesses to our best-in-class regulated portfolio. We continued progress towards successful resolution for both Millstone and ACP and we’ve advanced capital programs that will help to support 5% plus earnings growth for the next decade. With that, we are happy to take your questions..

Operator

[Operator Instructions] Our first question comes from Shahriar Pourreza with Guggenheim Partners. .

Shahriar Pourreza

Hey, good morning guys. .

James Chapman

Good morning..

Thomas Farrell

Good morning. .

Shahriar Pourreza

So, couple questions here. First on sort of Millstone, obviously you are excluding the zero carbon procurement in your outlook. Is this a pricing issue given what’s currently proposed, i.e. it’s not very accretive to your growth or are you kind of implying that a closure is still in the mix if you get the pricing as currently proposed.

So, just trying to figure out why it’s been excluded?.

James Chapman

Hey, Shahriar, it’s Jim, good questions..

Shahriar Pourreza

Hey, Jim..

James Chapman

So, the way we think about that is that, looking the table right now, as you know within this ten year contract for the first three years, basically, roughly equivalent to market pricing. So, no need for us to have a contract for that.

So, we are hopeful that there will be a contract for that period and value of these other attributes we’ve talked about for Millstone. So if that comes into play, the contribution from such a contract for the relative period would be an adder to our guidance – earnings guidance.

It doesn’t necessarily mean that we change our growth rate but will be an adder to the existing guidance. So that’s what we mean by that that’s excluded. There will be a potential for an adder for the time period in which an acceptable contract comes into play..

Shahriar Pourreza

Okay.

Is it tellable for you as currently proposed or is there – or is sort of a shutdown still something that’s in the potential given what you assume?.

James Chapman

Sure, we have a new administration in place. We have been working very constructively with them. So, I am not going to – we are not here to do any stable rattling today. Our position hasn’t changed. We have to have a clear financial path for Millstone that proposals from Governor Malloy’s outgoing proposal does not meet that standard..

Shahriar Pourreza

Got it, okay good. And then, Tom, let me just ask you and you touched on in your prepared remarks around the economics of sort of the pipe Atlantic Coast especially with the second delay and cost increase.

Can you just be a little bit more specific on how the conversations are going but more importantly what sort of the impact this sort of legislation, I think it’s bill number 17, 18 that’s advancing to the General Assembly.

Is there viability to this thing into and just what are your thoughts there?.

Thomas Farrell

Well, so, I think that’s two different questions in that.

As I understand, the first one is about, are you talking about conversation with customers?.

Shahriar Pourreza

Correct, correct. .

Thomas Farrell

Okay, I’ll let Diane answer that question just a second, Diane Leopold. With respect to the legislation, I would just say, I think the simplest answer to say that legislation has a long way to go in the general assembly. .

Diane Leopold Executive Vice President & Chief Operating Officer

And, good morning, this is Diane Leopold.

With respect to the contract, there are provisions in the contract to discuss both rates and terms and as Tom discussed, given the latest schedule and pause that we talked about today, we are already working with customers to set these rates and terms, partial in-service options, the actual rates for the service et cetera.

And we are confident we are going to be able to balance the customer needs and provide them with their critical need for this project in both cost and non-cost items while preserving a fair return for the project, but we really don’t want to go into anymore details on that..

James Chapman

And let me add just one thought also on the legislation. I think it’s also fair to say that, in this present – it’s not likely to come through the general assembly process in its present form. .

Operator

Thank you. Our next question comes from Steve Fleishman with Wolfe Research. .

Steven Fleishman

Yes, hi, good morning. Thanks.

So, just to follow-up on the ACP contracts, Tom, you mentioned the $1.79 decatherm last five years, just could you give us a sense of where the contract pricing of ACP is now versus that?.

Thomas Farrell

Nom, Steve, we can’t. That’s all through confidential agreements with the customers. But I....

Steven Fleishman

But it’s a lot better, yes..

Thomas Farrell

It’s significantly lower than $1.79..

Steven Fleishman

Yes, okay.

And then, what is pricing more like now as opposed to the last five years is it in that ballpark too?.

Diane Leopold Executive Vice President & Chief Operating Officer

Yes, I mean, the last few days when it was cold, it wasn’t just cold on the East Coast, obviously as it was on the Midwest. But I believe it was somewhere $5, $6 versus the Henry Hub, it certainly has value there. But that five year average actually is summer and winter time.

It is average through the entire year, not just the price spikes of the winter..

Steven Fleishman

Right, okay. .

Diane Leopold Executive Vice President & Chief Operating Officer

So, it continues to show value and increase that you see in these cold times..

Steven Fleishman

Okay.

And then, just in terms of going back to – there was a question - I just want to clarify the comments on the convert, so that your intention is to issue a new convert when that one is done or just re-market the debt?.

James Chapman

Yes, good question. We are required based on the terms of existing units remarketed to debt. That doesn’t represent the increase in debt. It’s just remarketing which will be this year. But this is our last outstanding mandatory convertible securities.

The equity converts into common equity, that going about in August and we view that as an attractive security to us and we think there is demand for us and the capital market is our perception. So we do plan to replace it. It will be exactly the same as the securities we have issued in the past, it could be slightly different.

But some form of that hybrid capital, mandatory convertible otherwise we plan to use to replace the $1.4 billion that effectively goes away in the middle of this year in August. .

Steven Fleishman

And then, one last question just back to ACP. So, I think there has been some concern that it’s often hard to get an en banc hearing, but obviously this is obviously a pretty important case.

So just, maybe you could give some color on why this – it might be different this time and your ability to get that hearing in this case?.

Thomas Farrell

Well, I would say, this is Tom, you are quite right, en banc proceedings are, they don’t happen every day of the week, they don’t happen every month. This case, I don’t know if you had a chance to read the brief that was filed on behalf of ACP last week.

And I think it sets the story out pretty well that there is a fifty pipelines that go on and meet the Appalachian Trail today, or it’s about 50 that are now all in question. We have significant support from a variety of folks. I think you will see ten or more friends of the court file a brief or briefs sometime late next week.

The Department of Justice will weigh in before February 11 on the importance of this. But that’s – we’ll see what happens. There is other avenues, as I mentioned, there is you can always appeal the Supreme Court, obviously.

Again, there is legislative efforts underway and there are other potential administrative avenues we are looking at that we haven’t been able to pursue very thoroughly, because of the government shutdown. But the en banc is important milestone.

But it’s not by any stretch the only avenue to make sure we finish this pipe in which we are highly confident. .

Operator

Thank you. Our next question comes from Rose-Lynn Armstrong with UBS. Mr. Armstrong, if your line is muted, you’ll need to unmute to ask your question..

Rose-Lynn Armstrong

Hello. You talked about discussing long-term dividend growth. .

Thomas Farrell

I am sorry, was that a question? I am sorry, I didn’t hear the whole thing..

Operator

I am sorry. It looks like she accidentally disconnected her line. .

Thomas Farrell

Okay..

Operator

We will go to our next questioner, Greg Gordon with Evercore ISI..

Greg Gordon

Good morning guys. So, thanks for the updated guidance range. I know that you had given sort of an interim guidance update in early January. And the illustrative guidance range at the time for 2020 it was 4.35 to 4.47.

Now if I did take the current guidance for 2019 and I just extrapolate 5% growth around, should I be extrapolating 5% growth just from the low and high-end to come up with? Would you guys believe your current 2020 implied guidance range should be to get the low-end or the high-end? I just want to be clear on that..

James Chapman

Yes, Greg. It’s actually, Jim. We are not really talking about a guidance range for 2020 yet. We have given this indicative 5%. So we think about it more in terms of midpoint. So, midpoint 2019 to 2020 that’s where our minds are right now. We will get more granular with the guidance range as we go through time. .

Greg Gordon

Okay. I just wanted to make sure that I was translating that 2020 statement properly. So, thank you. I appreciate it. In terms of other questions, I think, most of mine have been answered. So, I’ll give you back the time. Thank you..

Thomas Farrell

Thanks, Greg..

Operator

Thank you. Our next question comes from Christopher Turnure with J.P. Morgan..

Christopher Turnure

Good morning, guys. Tom, you mentioned the alternative plan for ACP and the slightly higher cost estimate and longer timeframe for that.

Could you just expand upon the exact permit scenario that would underpin that plan?.

Thomas Farrell

We have all of our permits. So, let’s – we didn’t mention in the script, for example, we did get our last real permits, significant permit which is the air permit for the Buckingham compressor station. So, what now is in front of us is these court challenges on variety of pieces.

No challenge for what’s between Buckingham County and Lumberton North Carolina. That’s with these issues in the mountains and the national parks et cetera. So, all those different timeframes and the different amounts are based on different scenarios on when we finish the court challenges. .

Christopher Turnure

Okay, so there is not one particular path there. So, it will be alternative if not if you fail at the en banc, then you do that. .

Thomas Farrell

Correct. There are other – there are multiple paths here. And I know, people are focused understandably and justifiably on the en banc. But that’s not the only path here. There are – there is the potential if we don’t get the en banc or we lose the en banc, there is the – we have the judicial path to Supreme Court.

There is legislative path that we are working on quite vigorously and there are, as I mentioned, administrative path that we have identified, but haven’t been able to fully pursue because of the government shutdown. But the primary focus right now for us is our en banc proceeding.

We face that decision as erroneous and a bench almost 50 years of agency precedent. .

Christopher Turnure

Okay.

And then, just following up on the strategy here with ACP, the biological opinion is, I guess, technically, what’s caused the temporary stop in construction right now? What I am wondering, given the gravity of the forest service opinion and the en banc process, were do not succeed on the forest service side, call it, in the second quarter or mid-year.

Does it make sense to continue construction at that time or hold off on construction until you get more clarity there? I think last time I checked you had drawn around $1 billion of the project level debt so far where you’ve spent a good amount but you are not, maybe, fully committed at this point in terms of spending in my opinion..

Thomas Farrell

Well, I’ll let Jim give you the numbers on what has been spent. I just – there is so many variables in that question. I just think it’s hard for us to really to answer it. We’d have to see – I think we are going to win on the biological opinion issue quite – but I have high confidence in that.

This is the second time around they followed the dictates of the court and what the court was interested in and reissued it. So, we would have to see we assume it’s going to get affirmed and if it’s not, we will have to see what the court said and then we’ll have to make a decision around that.

But we think all of that is taken into account in these different timeframes given here, because we can proceed from Buckingham which is sort of almost middle of the pipeline, all the way down to Lumberton and up into Hampton Roads. .

James Chapman

Hey, Chris, let me just add, you mentioned correctly that back in October, when we published our third quarter Q, we noted that the amount of capital drawn on this project level construction facility was a little over 1, 1.5 I think it was really on a 100% basis. I am sure that number as of 12/31 is about 1.4 not drastically different.

That’s on a 100% basis, so, that would imply total spend, that’s of course 50% of the cash capital is represented and drawn on the project level facility. So it double to get on a 100% basis the total amount spent which will be about approaching 2.8 as of 12/31. And those numbers will be more so in the case. .

Operator

Thank you. Our next question comes from Rose-Lynn Armstrong with UBS. .

Thomas Farrell

Here you are..

Rose-Lynn Armstrong

Hi, I will try again..

Thomas Farrell

I think you got cut-off in the middle of the question. I am sorry. .

Rose-Lynn Armstrong

I did. I apologize.

So, getting to the indication earlier that you would discuss long-term dividend growth at the Analyst Meeting, can you just give us a little preview of that today? I believe previous comments regarding 2020 were that the policy was predicated on the MLP market and now of course with the rollout, how are you thinking about dividend policy going forward?.

Thomas Farrell

Thanks Rose-Lynn. Let me just refresh everybody on the background here. So, we announced that expected dividend policy – of course they are all subject to, as you all know, each quarter to Board approval. But we said in 2017 that looking forward we had a very robust MLP market. We had Cove Point expectations coming online et cetera.

Because of the unique nature of the take or pay contracts with Cove Point, very significant cash flows flowing out of that with the recapture of the capital cost that we would see through drops into the MLP that we would grow the dividend 10% a year in 2018, 2019 and 2020.

And then, when we got to 2021, we have to see what the landscape looks like at that time. After the FERC ruling, in March of last year that destroyed the viability of the MLP market. Over time, we said not too long after that date I don’t remember the exact date, Rose, and we said something along the lines that we are going to keep 10% in 2018.

We expect to keep 10% in 2019. And depending upon what happened people are going to ask FERC to reconsider. We didn’t know what exactly was going to happen that it could go from 6% to 10% depending upon what happened with MLP. I think we had since said that the expectation obviously the MLP market is no longer there.

So you are already at the bottom of that. But, we recognized that it’s not going to be 10% in 2020, highly unlikely and over time, we will bring the dividend growth rate, not going to be a cut in our dividend, that’s not even in contemplations, the notions will bring our growth rate of our dividends more in line with our peers after this year.

So starting in 2020, some – and I will talk more about that in March, but there will be some effort to bring them more in line with our peer group. I don’t know if that answers your question, I hope it does. .

Rose-Lynn Armstrong

Okay.

And you think – what’s your – I guess, if we look at it from a payout ratio perspective, can you talk about where you would hope to see the payout ratio will return?.

James Chapman

Hey, Rose, it’s Jim. We will talk about that at the end of March. But we will be setting the dividend growth rate to reach a target payout ratio that’s more in line with peers..

Rose-Lynn Armstrong

Okay. Thank you. .

Operator

Thank you. Our last question will come from Jonathan Arnold with Deutsche Bank. .

Jonathan Arnold

I think you just answered one of our questions which, Jim, it’s the payout that you’d bring in line with peers and not the growth rates.

I just want to be clear that that if we are understanding you correctly on that?.

James Chapman

That’s exactly right. That’s exactly right..

Jonathan Arnold

Okay. And peers, you’ll, so share with us what you view the right grid to be in the March meeting presumably..

James Chapman

Exactly..

Jonathan Arnold

Okay. And then, just on ACP, when you guys are talking about customers, are you – does that include the anchored kind of utility customers? Your facility of customers and does whatever you have negotiated with them needs to be approved by the state regulatory bodies, I am just curious on that..

Diane Leopold Executive Vice President & Chief Operating Officer

The discussions are with – sorry, this is Diane Leopold. The discussions are with all of the customers and every customer has something different with respect what they will need to finalize the deal. But we are in active discussions with all the customers now. .

Jonathan Arnold

And then, to the question of, is it subject to SEC approval outside or normal?.

Thomas Farrell

You are talking about – when you say, SEC you are referring to, in Virginia?.

Jonathan Arnold

Yes. .

Thomas Farrell

In Virginia, it’s just a matter of – it’s like any other part of fuel cost. So that will be part of the fuel cost case in whenever 2021 or 2022 along with all the other ins and outs of our fuel cost. .

Jonathan Arnold

Perfect, okay. Thank you, Tom..

Thomas Farrell

You are welcome. .

Operator

Thank you. Ladies and gentlemen, this does conclude this morning's conference call. You may disconnect your lines, and enjoy your day. Thank you..

ALL TRANSCRIPTS
2024 Q-3 Q-2 Q-1
2023 Q-4 Q-3 Q-2 Q-1
2022 Q-4 Q-3 Q-2 Q-1
2021 Q-4 Q-3 Q-2 Q-1
2020 Q-4 Q-3 Q-2 Q-1
2019 Q-4 Q-3 Q-2 Q-1
2018 Q-4 Q-3 Q-2
2017 Q-4 Q-3 Q-2 Q-1
2016 Q-4 Q-3 Q-2 Q-1
2015 Q-4 Q-3 Q-2 Q-1
2014 Q-3 Q-2 Q-1