Thanks, Todd, and good morning, everyone, and thank you for joining. During today's call, I'll discuss our 2025 accomplishments, recap the strategic milestones DTM has achieved since our spin-off approximately 5 years ago and provide an update on our organic growth project backlog and our outlook for 2026 and beyond. I'll then close with some observations on the current natural gas market fundamentals before turning it over to Jeff to review our financial performance and guidance. So with that, 2025 was another record year for DTM. Our adjusted EBITDA exceeded our increased guidance midpoint and represents a 17% increase from the prior year, driven by significant growth in the Pipeline segment, which has been a strategic focus for the company since we spun. The end of 2025 also marked 1 year since our Midwestp pipeline acquisition, and I'm very pleased to report that we have successfully completed the integration of these assets. And I'd like to take a moment to recognize and thank the team for their hard work on this effort. From a commercial perspective, last year, we advanced more than $1 billion of organic opportunities from our backlog, of which 80% is for pipeline projects. On the construction front, we continued our successful track record of project execution. Most notably, our construction team placed the LEAP Phase 4 expansion into service early and on budget, increasing the capacity of LEAP to 2.1 Bcf per day. Additionally, we placed several gathering projects into service across our footprint, which enabled us to achieve record high throughput in 2025. We also continued our disciplined financial management, prioritizing a strong balance sheet and achieved investment-grade credit ratings across all 3 rating agencies. So I am very pleased with our overall performance last year, which reflects the continued focused execution of our core strategy, pure-play natural gas, leading contribution from the pipeline segment long-term demand-based contracts and a high-quality portfolio of strategically located assets. Since we spun the company nearly 5 years ago, DTM has consistently outperformed the broader market and our midstream peers, delivering total shareholder return of approximately 280%, including 12% compounded annual adjusted EBITDA growth and a consistently growing and durable dividend. Our high-quality natural gas pipeline segment has driven this growth, increasing from 50% of our business to 70% today, the highest among our peer group. Our portfolio continues to be well contracted with 95% demand-based agreements and an average contract tenure of 8 years, which reflects how the market values these assets and our ability to continually replenish the contract tenor. We have also successfully executed focused, strategic bolt-on acquisitions that have increased our ownership in regulated pipeline assets. All of these great accomplishments could not have been achieved without the hard work and dedication from our team to whom I am forever grateful and who continue to be the foundation of our success. Their commitment to safety, performance excellence and customer service are core elements of our exceptional results, and I'm excited for the future and our ability to deliver on the tremendous opportunities ahead. Turning to 2026 and beyond. We are very well positioned within the natural gas ecosystem to serve the increasing demand across our footprint, and continue our track record of premium, high-quality natural gas pipeline growth. Supported by strong fundamentals, we are embarking upon a window of generational investment opportunities and have updated our overall organic project backlog to reflect this, increasing it by approximately 50% to $3.4 billion over the next 5 years, with pipeline projects leading the way, comprising approximately 75% of the backlog. Our growth backlog represents our FID projects and probability-adjusted future organic opportunities that we are committing to execute on and can be fully funded with our strong cash flows and healthy balance sheet. The gross backlog is much larger, which is an indicator of the extraordinary opportunity set that exists. We will continue our prudent capital allocation through this investment cycle and expect to deliver growth above our long-term growth rate guidance in the later part of the decade, driven by sizable projects being placed in service. With that, I'm pleased that 2026 is already off to a great start, and we are announcing that we've reached FID on 2 new projects in our Pipeline segment. The first is an expansion of Viking to serve low growth in Grand Forks, North Dakota, and is anchored by an investment-grade utility customer under a long-term negotiated rate contract and is expected to go into service in Q4 2027. The second is our next phase of Interstate Pipelines modernization program, which will be focused on Midwestern pipeline, and will improve the reliability of this critical capacity serving the market corridor between Chicago and Nashville. With these projects commercialized, we have approximately $1.6 billion committed out of our $3.4 billion backlog. We are also advancing additional pipeline projects towards FID. Vector Pipeline closed a successful binding open season for an expansion to increase westbound capacity into Chicago by approximately 400 million cubic feet per day and has a contractual support needed to move forward subject to final approvals from both owners and is expected to be in service in Q4 2028. Millennium Pipeline has obtained contractual support for the R2R project as the long-term agreements have been executed with 2 utilities and an existing power plant. Subject to final approvals from both owners, the project is expected to be fully in service in Q1 2027. We will provide more updates once these projects are formally approved. Turning to project construction. We placed the Stonewall Mountain Valley pipeline expansion into service early and on budget at the beginning of February, and deliveries are being made to Mountain Valley for multiple customers. In addition, our Phase III Appalachia gathering system expansion has now reached full in service, also early and on budget. All other previously announced growth investment projects remain on track and on budget. Finally, I'd like to take a moment to provide our view on the natural gas market fundamentals. Natural gas has firmly established itself as a core North American fuel, offering unmatched affordability and reliability, lower emissions and the security of a domestic resource base. It underpins the onshoring of manufacturing, rapid data center development and the continued build-out of LNG exports, all key drivers of long-term demand and foundational to America's global competitive posture. With these tailwinds, the stage is set for specific opportunities driving our strategy, and we are seeing these strong structural demand signals across our operating footprint. Demand for natural gas to serve power continues to accelerate across the Upper Midwest with approximately 35 gigawatts of coal plant generation expected to retire in the next 10 to 15 years, and increasing announcements of new large loads and data centers being cited. This demand is largely going to land with utilities in these states who have announced contracted and potential large load opportunities of approximately 50 gigawatts and are planning to invest close to $150 billion in new generation over the next 5 years to keep pace below growth. These are large numbers. And while not all power demand will be served by natural gas, we see an addressable opportunity set of up to 13 Bcf per day and a pathway that could easily result in 5 to 8 Bcf per day of potential incremental gas demand in the upper Midwest. DTM's extensive interstate gas pipeline network is uniquely located across this region and is already serving many of the utilities that will experience this low growth, positioning us to fuel many of these opportunities. On the LNG front, we saw 4 terminals reach FID in 2025 as well as international companies vertically integrating in the Haynesville to extend their natural gas value chain, both of which will support strong and sustained export demand. We expect LNG demand to grow by 11 Bcf through 2030, with 2/3 being served by the Haynesville. In our integrated system with its leading connectivity to both supply and demand markets is exceptionally well positioned to capitalize on the strengthening trends. I'd also like to address the recent cold weather. It has illuminated the tightness that exists today in the North American market, resulting in extreme price volatility across our entire footprint, a signal of capacity constraints driven by demand growth. The natural gas pipeline and storage network performed very well during the cold, demonstrating its reliability to serve its existing firm customers. However, the price volatility is a strong signal that we need to build and expand the pipeline network to bring more natural gas to serve the growing demand. For DTM, this winter, our storage complex recorded all-time high withdrawals, and many of our pipelines experienced record high peak day throughputs. Pulling this all together, today's natural gas market fundamentals makes DTM's natural gas infrastructure critically important and positioned for growth. And with that, I'll pass it over to Jeff to walk you through our financial results and outlook.