Thank you, John. Good day, everyone, and thank you for joining our call. I will begin by summarizing our announced series of development projects we expect to materially contribute to Montauk's multifaceted growth strategy. In December 2023, we finalized a contract for the delivery of 140,000 tons per year of biogenic carbon dioxide from our four Texas RNG facilities to a North American subsidiary of European Energy. In satisfaction of this arrangement, we intend to capture clean and liquefied CO2, which will then be transported to a new Texas-based e-methanol facility of European Energy. The delivery term is expected to last at least 15 years with deliveries expected in 2027. We expect our capital investment to approximate $15 million per facility and anticipate that capital spend to begin during the second half of 2024 as we work to achieve our targeted 2027 commission. During 2023, we announced our planned entrants into South Carolina through the development of a new landfill gas to RNG facility, an opportunity won by Montauk through a competitive bidding process. The planned project is expected to contribute approximately 900 MMBtus, a day of production capacity upon commissioning. We are in the development phase of the project and have started to incur capital expenditures. While we continue to expect the utility interconnection specifically included in our development assumptions to accept our production from this facility, the utility will require certain distribution system upgrades. Though those upgrades do not directly impact our interconnection, they do extend our expectation of the completion of that interconnection and the commissioning of our new RNG facility into 2026. During 2023, we also announced our planned development of a landfill gas to RNG project in Irvine, California at the Frank R. Bowerman Landfill. This new RNG facility is anticipated to process the large and growing volumes of biogas in excess of the existing capacity of our existing renewable electric generation facility on the Bowerman Landfill, which we intend to both retain and operate alongside the new RNG facility. As previously disclosed, we continue to expect the capital investment to range between $85 million and $95 million and anticipate the fully commissioned facility in 2026 to contribute approximately 3,600 MMBtus per day in production capacity, assuming currently forecasted bio stock -- feedstock volumes that are projected to be available from the host landfill at the time of commissioning in 2026. I will now shift to an update on our various ongoing growth development projects, starting with our digestion capacity expansion of our Pico dairy cluster project in Idaho. As previously disclosed, our dairy host began delivering the first 2 of 3 feedstock increases identified in our feedstock amendments, the catalyst for the expansion project. Also, as previously disclosed, 3 of the 4 development payments were made to our dairy host related to those achieved feedstock increases. Our dairy host informed us that they expect to deliver the final increase in feedstock volumes in 2025, at which time we will make the final development payments. The California Air Resource Board approved, after the public comment period ended in March 2023, our provisional carbon intensity score application with a CI score of negative 261.56. We released the remaining gas from storage in the second quarter of 2023 and recognize both RIN and LCFS credit revenues related to those storage releases during 2023. Regarding the physical commissioning of our Pico dairy digestion capacity increase project, we successfully commissioned the first of two new digesters as well as our new reception pit, both of which became operational during the third quarter of 2023. We immediately began using the increased reception pit capacity and have been working to increase gas availability through the additional digestion capacity. We continue to commission the second and last of our new additional digesters expect to complete commissioning during the second quarter of 2024 and increased gas availability into the third quarter of 2024. We continue to expect our digestion capacity expansion project will allow us to take advantage of the excess capacity in our existing RNG facility at this location. I will now discuss the many developments we have had related to our North Carolina swine waste energy development, Montauk Ag Renewables. We continue to work with our engineer of record through the optimization of improvements to our patented reactor technology. During the first quarter of 2023, we completed the relocation of our existing reactor from its original location in Magnolia, North Carolina to our new Turkey, North Carolina facility in an effort to centralize future feedstock processing. We executed a receipt interconnection agreement with Piedmont Natural Gas for our Turkey, North Carolina location. Related to our interconnection, we signed a lease agreement with Piedmont Natural Gas to provide access to the Turkey, North Carolina property during the construction of the interconnection. In July 2023, we signed a Renewable Energy Certificate, REC agreement, with Duke Energy, Duke, under which, Duke will purchase the swine waste RECs from the conversion of swine waste feedstock into renewable energy. During the third quarter of 2023, our Board of Directors approved funding for the first phase of our development initiative in North Carolina. We continue to expect the first phase total capital investment to range between $140 million and $160 million, which includes approximately $33 million of cumulative expenditures through the end of 2023. We continue to expect the first of our eight processing lines of this first phase to be operational in the second quarter of 2024, and we are currently planning for a rolling commissioning schedule for the remaining processing lines beginning in the second half of 2024 through the second half of 2025 with revenues beginning in 2025. Our Turkey, North Carolina project location was approved to participate in the Piedmont Natural Gas Renewable Pilot Program, which is a step towards obtaining the new renewable energy facility NREF designation under the North Carolina Utilities Commission, the NCUC. In January 2024, we received notification from the NCUC that our Turkey, North Carolina location was approved for both our NREF and a Certificate of Public Convenience and Necessity. This is a critical step towards obtaining the NREF designation and obtaining this designation could have an impact on the timing of utility infrastructure at our Turkey, North Carolina location. In March 2024, we submitted an amendment to our NREF designation to optimize its applicability to specific facility componentry for which we expect a decision on that amendment during 2024. Upon completion of our first full phase of the Turkey, North Carolina project, we anticipate the ability to process feedstock from over 120,000 hog spaces per day, equating to over 200 tons of daily waste collection per day. We continue to expect to annually produce approximately 45,000 to 50,000 megawatt hour equivalents through the combination of 190,000 to 200,000 MMBtu and 25,000 to 30,000 megawatt hours. Additionally, we continue to estimate the first phase of the project will produce 17,000 to 20,000 tons of organic fertilizer alternatives annually. During 2022, we announced our plans to construct a second RNG processing facility at the Apex landfill. This project is being driven by projections of biogas feedstock availability from the host landfill. As the landfill host continues to increase its waste intake, we believe that the additional 2,100 MMBtu per day of production capacity of our new facility will allow for us to process the landfill hosts currently forecasted increases in biogas feedstock volumes related to their projected increases in waste intake. While the landfill host continues to increase waste intake, we expect there could be a period where we have excess available capacity after the second facility is commissioned. We currently expect commercial operations during the fourth quarter of 2024. In 2024, we reached an agreement with one of our landfill hosts to sell back our gas rights in advance of their expiration impacting one of our smaller renewable electric generation operating facilities. The strategic decision to exit this facility was influenced by a mid 2024 expiration of an above market power purchase agreement. The elimination of decommissioning asset removal or site restoration obligations, the sale proceeds of $1 million being well in excess of the carrying value of this project and the offer to extend our gas rights at two of our existing RNG operating facilities, Atascocita and Coastal Plains, for an additional 5 years each. The effective date of this transaction will be October 1, 2024. And with that, I will turn the call over to Kevin.